Areas 2, 3, 4 & 5 |
|
January 7,
2002 | |
|
|
|
|
|
RFP Notice-to-Proceed April 27, 2001 |
|
RFP Design Complete November 30, 2001 |
|
Notice-to-Proceed - June 11, 2001 |
|
The 30 % submittal -August 21, 2001 |
|
The 90% submittal - November 26, 2001 |
|
The 100% submittal - scheduled for January 15,
2002 | |
|
|
|
|
|
Advertise for Construction Bids - February
2002 |
|
Bid Opening March 2002 |
|
Public Information Meetings in April and May
2002 |
|
Final vote to Form Assessment District May
2002 |
|
Begin construction June/July 2002 (Completion
November 2004) |
|
| |
|
|
|
|
|
City of La Canada Flintridge |
|
Los Angeles County Department of Public
Works |
|
Los Angeles County Sanitation District |
|
Caltrans |
|
SWRCB |
|
| |
|
|
|
|
|
La Canada Irrigation District |
|
Valley Water Company |
|
Southern California Gas |
|
Southern California Edison |
|
Charter Communications |
|
La Canada Unified School District |
|
| |
|
|
|
|
Reports required to be filed |
|
Draft Project Report and Revenue
Report |
|
Environmental Document |
|
Water Conservation Plan |
|
Loan
Application | |
|
|
|
Modified Report for Area 2 only |
|
Submitted December 2001 to SWRCB |
|
| |
|
|
|
|
Public Review Period
Completed |
|
State Clearinghouse Review
Complete |
|
Ready to Publish Notice of Public
Hearing |
|
Hold Public Hearing to consider approving
the Initial Study/Negative Declaration |
|
If approved submit Council Resolutions to
SWRCB |
|
| |
|
|
|
Demonstrates the City will comply with a water
conservation plan |
|
Documentation filed for Assessment District No.
98-1 is sufficient, no further reporting is
required. | |
|
|
|
|
Project costs and estimate of annual
expenses |
|
A schedule of project
milestones |
|
Sources of loan repayment |
|
Resolution of intention for dedicated source of
revenue |
|
Resolution authorizing ongoing revenue
source |
|
Resolution authorizing a representative
to execute the contract (For Area 1 it was the City
Manager) |
|
Right of way identification and
acquisition status |
|
Certificate of Compliance with Federal
Laws and Authorities | |
|
|
|
|
|
|
|
Start Aerial Mapping in January 2002 |
|
Preliminary Design Starts–February
2002 |
|
Hold Study Sessions in May and June
2002 |
|
City to hire independent firm to Conduct
Preliminary Vote for Area 3 in June 2002 |
|
If approved Final Design Begins in July
2002 |
|
Final Design Complete February
2003 | |
|
|
|
|
|
Advertise for Construction Bids - March
2003 |
|
Bid Opening April 2003 |
|
Public Information Meetings in April and May
2003 |
|
Final vote to Form Assessment District May/June
2003 |
|
Begin construction July 2003 (Completion November
2005) |
|
| |
|
|
|
|