Citywide Sewer Project Update
Areas 2, 3, 4 & 5
January 7, 2002
Area 2 Schedule
RFP Notice-to-Proceed April 27, 2001
RFP Design Complete November 30, 2001
Notice-to-Proceed - June 11, 2001
The 30 % submittal -August 21, 2001
The 90% submittal - November 26, 2001
The 100% submittal - scheduled for January 15, 2002
Area 2
Advertise for Construction Bids - February 2002
Bid Opening March 2002
Public Information Meetings in April and May 2002
Final vote to Form Assessment District May 2002
Begin construction June/July 2002 (Completion November 2004)
Area 2 Plan Review
City of La Canada Flintridge
Los Angeles County Department of Public Works
Los Angeles County Sanitation District
Caltrans
SWRCB
Area 2 Plan Review
La Canada Irrigation District
Valley Water Company
Southern California Gas
Southern California Edison
Charter Communications
La Canada Unified School District
Loan Commitment
Reports required to be filed
Draft Project Report and Revenue Report
Environmental Document
Water Conservation Plan
Loan Application
Draft Project Report and Revenue Report
Modified Report for Area 2 only
Submitted December 2001 to SWRCB
Initial Study/Negative Declaration
Public Review Period Completed
State Clearinghouse Review Complete
Ready to Publish Notice of Public Hearing
Hold Public Hearing to consider approving the Initial Study/Negative Declaration
If approved submit Council Resolutions to SWRCB
Water Conservation Plan
Demonstrates the City will comply with a water conservation plan
Documentation filed for Assessment District No. 98-1 is sufficient, no further reporting is required.
Loan Application
Project costs and estimate of annual expenses
A schedule of project milestones
Sources of loan repayment
Resolution of intention for dedicated source of revenue
Resolution authorizing ongoing revenue source
Resolution authorizing a representative to execute the contract (For Area 1 it was the City Manager)
Right of way identification and acquisition status
Certificate of Compliance with Federal Laws and Authorities
Assessment District Proceedings
Areas 3A & 3B Schedule
Start Aerial Mapping in January 2002
Preliminary Design Starts–February 2002
Hold Study Sessions in May and June 2002
City to hire independent firm to Conduct Preliminary Vote for Area 3 in June 2002
If approved Final Design Begins in July 2002
Final Design Complete February 2003
Areas 3A & 3B
Advertise for Construction Bids - March 2003
Bid Opening April 2003
Public Information Meetings in April and May 2003
Final vote to Form Assessment District May/June 2003
Begin construction July 2003 (Completion November 2005)
Estimated Timetable Month/Year
Questions